Table of Contents:

Overview

Part 1

Part 2

Part 3

Electrical

Fuel Systems

Fuel Systems - Table of Contents

Introduction

General

Equipment Standards

Manufacturing Requirements

Tests

Figures & Tables

Appendix A

Appendix B

Ventilation

Safe Loading

Flotation

Downloads

Fuel Systems

Appendix A — Fuel System Standard

16.0 — Lab Examination No. 12
Fuel Tank Shock Test cont'd

16.3 Test

16.3.1 This procedure shall be used to shock test metallic and non-metallic fuel tanks of any size and capacity. Fuel tanks which have a capacity of 25-gal. (94.6 l) or larger shall not be tested.

Verify the applicability of this procedure to the tank being tested before proceeding by filling the tank to its maximum capacity.

16.3.2 Visually inspect the fuel tank. Review the results of the Receiving Inspection (Data Form No. 1) and verify that the component is acceptable and ready for testing. Tanks that obviously would leak and have failed the pressure test, or those that do not have a proper label shall be rejected.

16.3.3 Verify that the fuel tank to be tested has successfully completed the static pressure test. If it has not been accomplished, the pressure test shall be completed at this time. Record whether the pressure was accomplished previously or is being completed at this time.

16.3.4 Non-metallic fuel tanks shall be filled to capacity with a gasoline that has at least a 50% aromatic content. ASTM Reference Fuel C meets this requirement. There shall be no evidence that the fuel tank has been adversely affected by the gasoline after 30 days at ambient pressure and temperature, but in no case less than a temperature of 70°F (21°C).

FIGURE: Shock Test — Typical Layout for Flat-Bottomed Tank
Test Schematic Procedure

FIGURE: Shock Test — Typical Layout for Non-Flat-Bottomed Tank
Test Schematic Procedure

16.3.5 Flush or purge the fuel tank with water and/or GN2 after the 30-day pre-conditioning test has been completed.

16.3.6 Verify that the shock machine to be used in this test has been calibrated to the specified g load and duration using a dummy load similar to the fuel tank to be tested.

16.3.7 Mount and secure the fuel tank to the platform of the impact test machine similar to an actual installation or similar to one of the following typical installations. Do not remove any attachments or fittings from the tank. Flat-bottomed tanks shall be mounted on a flat platform. Tanks with other than flat bottoms shall be mounted on chocks cut to fit under the ends of the tank and under the baffles, if any. See the Test Schematic for typical installations.

16.3.8 Fill in the tank with water to at least rated capacity. Cap and/or plug the fuel tank fill pipe and the fuel feed adapter. If a gasoline gauge is not installed, cap this opening. Leave the fuel tank vent pipe open to the atmosphere.

16.3.9 Fuel tanks installed in the forward half-length of the boat or labeled or intended for use in the forward half-length of the boat shall be subjected to 1000 cycles of 25 g vertical shock. Fuel tanks installed in the aft half-length of the boat or labeled or intended for use in the aft half-length of the boat shall be subjected to 1000 cycles of 15 g vertical shock. When in doubt about a fuel tank’s installation or usage, subject the tank to 1000 cycles of 25 g vertical shock. The duration of the shock pulse, measured at the base of the shock envelope, shall be 10 ±4 milliseconds. The shock shall be applied at a rate of 80 cycles or less per minute. The test parameters shall be monitored by suitable instrumentation mounted as near to the center of gravity of the fuel tank as possible.

16.3.10 The fuel tank shall be visually inspected after wach shock test has been applied. If any obvious failure has occurred, the fuel tank shall be rejected.

16.3.11 If the tank shows no indication of any leakage after 1000 shock applications, remove the tank from the shock machine and secure the system.

16.3.12 Perform the pressure test on the fuel tank and verify that the tank does not leak. If leakage is found during the test, the tank shall be rejected. If the tank successfully completes the pressure test, the tank shall be deemed acceptable according to the requirements of this procedure.

Previous  |  Next

 

USCG red rod