183.586 - Pressure impulse test

(b) If the tank is non-metallic, fill it to capacity with a gasoline that has at least a 50 percent aromatic content. Keep the fuel in the tank at 21 deg.C. or higher for 30 days prior to testing.

This test is performed on all tanks of 25 gallons or greater capacity.

Non-metallic tanks should be filled to rated capacity with a gasoline such as ASTM Reference Fuel C for a period of 30 days at a temperature of not less than 70ºF (21ºC).

This is a pre-conditioning for further testing.

Figure 43 - Pressure Impulse Test Applicability